High Voltage Cable at New Cross



Suspending the cable
Suspend the cable

Some of the infrastructure on the nation’s railways is old and in a delicate condition. Power + Line was retained to provide temporary protection to a high voltage cable at New Cross pending an upgrade to the local installation.

Due to the poor condition of the cable we began by building a cradle around it so that the existing structure was disturbed as little as possible.

This work was carried out according to plan and no problems occurred when the electricity current was turned on after the works were completed.

Build a trough to support the cable
Build a trough to support the cable

 

Close off and seal the trough route
Close off and seal the trough route